White Sands Missile RangeUS Army

White Sands Missile Range - WSMR High Speed Carrier

Project Title: WSMR High Speed Aerial Cable Carrier

Project Customer: United States Army / White Sands Missile Range


WSMR Army Huey on High Speed Cable Carrier
WSMR Army Huey on High Speed Cable Carrier
ACME SolidWorks™ Model of Carrier Upper Frame
ACME SolidWorks™ Model of Carrier Upper Frame

Project Overview: The development of a High Speed Aerial Cable Carrier (Carrier) for White Sands Missile Range (WSMR) was initiated with a one page statement of objectives, a verbal briefing by ACME identifying a technical approach, and contract award. All the activities occurred within 30 days.

WSMR has a test facility which consists of a 3 mile long high strength cable strung between two mountain peaks. Test articles are attached to a carrier and the entire assembly is pulled toward the higher peak along the cable to a predetermined position. Once there, the carrier is released from its transport trolley and accelerates down the cable due to gravity. This provides a moving target for test scenarios. It passes through the test envelope and then decelerates and stops before contacting the lower peak. During one of these tests, the cable, carrier, and test article were inadvertently shot down and destroyed. As a result, WSMR needed a replacement carrier to support future tests.

ACME Services Used: Mechanical Engineering, Systems Engineering.

Project Details:
The original carrier was designed as a single use device which required extensive manhours and refurbishment costs to prepare for an individual test. Additionally, it did not function very well and did not provide repeatable results. ACME's task was to design a robust, low maintenance carrier that could withstand 250 knot speeds with a 20,000 lb payload. Additional design requirements included a vibration suppression system, extensive on board instrumentation including video recording and GPS, and large power sources for the test article.

Another major design requirement was an efficient method of attaching the carrier to the cable. One of reasons that this project was notable was that there was no design precedent. When designing trainers, ACME uses lessons learned from previous programs. In developing the carrier, ACME had no precedent. Consequently, the development of the carrier exclusively depended on engineering analysis.

At program initiation, ACME immediately began a systematic systems engineering analysis of the problem. This analysis identified a variety of derived requirements and began bounding the physical constraints of the carrier. For example:

a) It had to withstand rocket thrust acceleration to achieve the 250 knot speed

b) It had to have redundant braking systems – both disk brakes on the carrier wheels and a parachute

c) It had to have the ability to put a reverse bend in the cable as it passed through the carrier to increase friction high enough to allow braking

d) The carrier could not damage the cable during operation (the cable costs in excess of $1M)

e) The installation of the carrier on the cable should not take more than 1 hour instead of the day and a half that it took to install the old carrier.

f) The carrier had to have a compound suspension at both the front and the rear in order to distribute the weight of the carrier and its payload equally among all the upper carrier wheels along the varying catenary angle of the cable.

After the carrier-derived requirements were better understood, ACME immediately began the hardware and software engineering necessary to design and develop the carrier. The software effort was concerned with development of a carrier instrumentation and control system. The hardware effort involved design of the structure, extensive finite element stress analysis, and development of the fabrication drawings. Finally, ACME initiated a parallel effort to develop acceptance test procedures and operating manuals. The carrier components were fabricated and assembled in the ACME shop. The resulting carrier design produced a device approximately 30 inches wide, 25 feet long, and 5 feet high. The top of the carrier was hinged and opened like a box so that it could be efficiently hung on the cable (it now takes about 20 minutes to attach the carrier to the cable). A pneumatic system is used to energize the vibration suppression bladders and to introduce the cable reverse bend. A blow down hydraulic system is used to control the disk brake system on 9 of the 13 carrier wheels. The carrier has dual on-board motor generators and a battery backup system to power the test article and on-board instrumentation and control system. Furthermore, the carrier has excellent equipment access and integral work platforms to facilitate field support of the carrier equipment.

ACME accomplished the design and development of the carrier in less than six months. The carrier was then relocated to the White Sands site where its operation was characterized (final acceptance testing). In short, the carrier exceeded all expectations. It was simple to attach to the cable, the vibration suppression system worked well, the braking system was reliable, the carrier aerodynamics showed that the new carrier was 17% faster than the old carrier under the same conditions, and, most notable, the carrier performance was highly repeatable with less than a 1% variation between standard runs. In fact, the carrier was so successful, WSMR ordered a second carrier and an ancillary equipment pod which attached to the bottom of the carrier.

Delivery Date: January, 1999

Customer Comments: N/A


About the Company |  Site Map  |   Testimonials  |   Contact Us

Site by: LionSkyMedia